If a project will take 35 employees 2940 hours to complete how many hours will each employee have to work

Respuesta :

afrazi01p8qv5j
afrazi01p8qv5j afrazi01p8qv5j
  • 02-07-2018
To find out how many hours each employee will need to work, we divide 2940 hours by 35 to evenly split the hours among each of the workers.
2940 / 35 = 84
This means that each employee will need to put 84 hours of work into the project to complete it.

Answer Link

Otras preguntas

what is the answer for (20,8),(9,16) ?
Historians of china have traditionally dated the beginning of Chinese civilization to the founding of the what??
find an equivalent expression without parentheses -(50x-15y+15)=
Prove that (x^5)-(x^2)+2x +3=0 has at least one real root. Prove that x=cosx has at least one solution.
how is mass transit in cities a possible solution tk urban air pollution?
How were life forms affected by the rise in atmospheric oxygen levels that began 2.2 billion years ago?
how is mass transit in cities a possible solution tk urban air pollution?
How is it possible for Mercury to have frozen ice ?
Data are drawn from a symmetric and bell shaped distribution with a mean of 120 and a standard deviation of 5. There are 900 observations in the data set. What
How is it possible for Mercury to have frozen ice ?