it takes 20 people 24 days to build a barn. in how many days will the barn be built if they had 32 people working

Respuesta :

bluevortexwitepower bluevortexwitepower
  • 02-02-2019

Answer:

15 days

Step-by-step explanation:

Number of ppl it takes to build a barn in 24 days=20

Time it will take 32 people to build the barn=24*20/32=15 days

Answer Link

Otras preguntas

PLZ HELP PLZZZZZZZZZ
18. The rescuers did not give upthey retrieve the body of the victims. A. Until B. While C. After​
An employee compiled sales data for a company once each month. The scatter plot shows the sales for the company over time. The equation represents the linear mo
You earn $6 per hour for pulling the weeds, you earned $15 last weekend. How many hours did you work last week?
In paragraph 64 and 72 of Kindertransport, Helga repeatedly uses the word "bad." What does this word choice reveal about Helga's wartime experience?
what does Polonius say Laertes is studying? politics war music math
Why might Bud need to be a better liar? From Bud, not Buddy use evidence.
The map shows the average high temperature in july for two cities in texas
Select the correct answer. What is the least common multiple of the numbers 5, 25, and 15? A. 25 B. 50 C. 75 D. 100 OE. 125
Solve this system of equations: 2x + 10y= 24 X = y-6