15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

Your parents put in fencing around the walkway for safety. If 110 feet of fencing is used, what are the dimensions of the pool?
Que Es 573.694 dividido enter 213
Solve for x 40 = x/ -4/7 ​
Customers tend to look at a business as a whole despite the number of ______ they experience.feedback surveyspurchasescomplaintstouch points​
PRACTICE Model Matit Jarrett walks his 360 puppy outside every day for 30 minutes. Angela walked her puppy every day for 90 minutes. Find the number of minutes
if electors officially choose the president what is the point of presidential election for the people
Which two numbers below have the least common multiple of 48? A. 4 and 16 B. 8 and 12 C. 8 and 24 D. 3 and 16
.1.3 Jennie has $200 and she spends $30. What percent of her money is spent? zoo A) 15% B) 30% 30 C) 66% D) 85%
Rewrite the equation from step 1 substituting in the value of.
According to Vonnegut, what does being American mean? Do you agree with Vonnegut when he says the burning of books is un-American? Why or why not?