If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

What is something a reflective presentation always does?Sometimes does?Never does?
Can y'all please help me with this? Thanks.​
What is the mode of the data represented in this line plot? Enter your answer in the box.
1. Analyze Structure What is the yellow struc- ture, and what role does it play in a cell?
why are sicissors concidered a first class lever
Explain the various types of speech that are protected by the First Amendment.
What is the 10th term of the sequence 12, -60, 300
could someone help me rnnn?
The statement below justifies an international action "The issue is the future of Southeast Asia as a whole. A threat to any nation in that region is a threat t
Complete Syd’s work to find the scale factor Scale factor = StartFraction scale drawing dimension over Original dimension EndFraction = StartFraction 7.5 over 3